Bobby Dodd Stadium Fan Experience Renovation

8/5/2025
-
Atlanta, Georgia

Georgia Institute of Technology

Buyer is seeking a construction management firm for the Bobby Dodd Stadium Fan Experience Renovation project. The project involves extensive renovation work scheduled between football seasons to minimize disruption. Construction is planned to begin after design completion in 2026 and continue through 2027. The renovation aims to enhance fan experience at the stadium while working within the constraints of active football seasons.

  • 8/5/2025 - Proposal Due Date
  • 8/22/2025 - Design Team Selection
  • 8/29/2025 - Construction Team Selection
  • 10/24/2025 - Schematic Design Completion
  • 12/19/2025 - Design Development Completion
  • 5/29/2026 - Construction Documents Completion
  • 6/26/2026 - Permitting Period
  • 8/28/2026 - Bid & Award Completion
  • 8/27/2027 - Construction Completion
Refer to RFP
  • Manage site supervision and construction team throughout the project
  • Coordinate safety and security measures for stadium renovation
  • Implement phased construction around football seasons
  • Provide project management during design development and construction documents phases
  • Set up and maintain site office and temporary facilities
  • Coordinate with architects and engineers throughout design process
  • Manage procurement of construction materials and equipment
  • Oversee cleaning and waste management during construction
  • Provide construction equipment including hoists and cranes as needed
  • Handle permitting and regulatory compliance