This RFP is currently open for proposals.
Sign up for an account to get RFPs matching your business in your inbox.

Design Services for Transmission Line and Substation

7/15/2025
-
Falls City, Nebraska

City of Falls City

Buyer seeks engineering services for 15 miles of 115 kV transmission line and a new 50 MVA substation. The project will establish a new interconnection point to the Southwest Power Pool via a 115 kV switchyard. Buyer requires expertise in high-voltage design, substation engineering, and project execution for municipal utility systems. The project is partially funded by the Nebraska Department of Economic Development and must comply with grant conditions.

  • 6/17/2025 - RFQ Published
  • 6/30/2025 - Questions Due
  • 7/15/2025 - Proposal Due Date
  • 12/31/2030 - Substantial Completion Estimated
  • Licensed professional engineers in Nebraska and Kansas
  • Experience in ROW acquisition and utility easement coordination
  • High-voltage transmission line routing and design experience
  • Substation engineering and equipment specification expertise
  • Environmental permitting and regulatory compliance experience
  • Construction management for utility-scale electrical infrastructure
  • Evaluate transmission interconnect options (looped vs. radial feed)
  • Assess potential substation locations
  • Provide guidance for SPP and NITS processes
  • Secure Network Integration Transmission Service Agreement
  • Support right-of-way acquisition
  • Create KMZ/KML or GIS-compatible shapefiles
  • Ensure documentation meets Nebraska licensing standards
  • Provide environmental consultants for permitting
  • Evaluate constructability and recommend phasing strategies
  • Align design milestones with grant administration