Central Utility Plant Chiller #5
University of Cincinnati
Buyer seeks engineering services to replace Chiller #5 in their Central Utility Plant with a machine of similar 5,000-ton capacity. The project requires evaluating the feasibility of one large machine versus two smaller machines and assessing 480V versus 12,470V power options. Maximizing efficiency is prioritized over maximizing capacity within the project budget. The plant provides chilled water, steam, and electric generation for the Uptown campus 24/7/365, requiring careful phasing to maintain continuous operations. Project must be completed by June 2027.
- 7/7/2025 - Proposal Due Date
- 9/25/2025 - Professional Services Start
- 2/1/2027 - Construction Notice to Proceed
- 5/1/2027 - Substantial Completion
- 7/1/2027 - Professional Services Completed
- Experience with central utility plants on university campuses
- Expertise in PLC-based building automation systems
- Structural engineering capability
- 3D scanning and BIM modeling experience
- Knowledge of chilled water systems
- Experience with 12,470V and 480V electrical distribution
- Equipment pre-purchase package experience
- State of Ohio contracting experience
- Life cycle cost analysis expertise
- Project scheduling experience
- Construction administration acumen
- Extensive cost estimating experience
- Develop Program of Requirements for chiller replacement
- Conduct 3D scanning of central plant
- Create BIM models for chiller layout options
- Assess electrical service needs against available capacity
- Evaluate structural design for new equipment
- Develop phasing plans for continuous 24/7/365 utility operation
- Design PLC-based controls integration for automation
- Prepare equipment pre-purchase package
- Evaluate refrigerant monitoring system for modifications
- Conduct feasibility study comparing 480V vs 12,470V chillers
- Perform life cycle cost analysis of options
- Provide 6 hours weekly on-site construction administration
- Coordinate with asbestos remediation documents
- Deliver schematic design through construction documents
- Create detailed cost estimates and schedules
- Provide structural analysis for piping systems
- Support bid and award process
- Ensure compliance with State of Ohio requirements
- Document existing conditions and validate them
- Prepare sequences of operations for automation