Heat Plant Smokestack Demolition

6/5/2025
-
Richmond, Kentucky

Eastern Kentucky University

Buyer is soliciting proposals for demolition of a smokestack at the Ramsey Heat Plant on main campus. The project involves phased demolition of the smokestack with strict milestone dates. The plant provides utilities to approximately 60% of university buildings, requiring careful planning and execution. Contractor must maintain access to critical areas throughout demolition process. Work includes site protection, demolition, drainage improvements, and restoration of affected areas.

  • 5/28/2025 - Mandatory site visit
  • 5/29/2025 - Questions due
  • 6/5/2025 - Proposal Due Date
  • 6/9/2025 - Work can begin
  • 6/24/2025 - Smokestack demo start
  • 10/7/2025 - Substantial completion
  • General Contractor
  • Specific Selective Demolition Experience
  • Develop detailed demolition sequence and means/methods for smokestack removal
  • Install roof protection systems to prevent damage to surrounding structures
  • Establish site control with fencing, signage, and equipment staging
  • Implement phased demolition to meet interim milestone deadlines
  • Create traffic management plan for maintaining campus access during demolition
  • Design and implement dust control measures for smokestack demolition
  • Coordinate utility protection for heat plant continuing operations
  • Develop vibration monitoring plan to protect adjacent structures
  • Create waste management and recycling plan for demolition materials
  • Restore access to critical areas according to milestone schedule