Construction Manager at Risk for Manchester Creek Wastewater Treatment Plant 30 MGD Expansion
City of Rock Hill
Buyer seeks a Construction Manager at Risk (CMaR) for the Manchester Creek Wastewater Treatment Plant 30 MGD Expansion. The project includes increasing treatment capacity from 20 MGD to 30 MGD with provisions for future 50 MGD capacity. Scope involves new equalization tanks, sequencing batch reactors, tertiary filtration, and modifications to chlorine contact tanks. Buyer requires preconstruction services beginning July 2025 through January 2026, followed by construction phases.
- 4/23/2025 - Solicitation Release Date
- 5/6/2025 - Pre-Proposal Meeting (Mandatory)
- 5/21/2025 - Question Submission Deadline
- 6/4/2025 - Proposal Due Date
- SC General Contractor's License
- Experience with projects over $30 million
- Experience with cast-in-place concrete basins and post-tension basins
- Conduct site logistics study for wastewater treatment plant expansion
- Evaluate construction sequencing and methods for 30 MGD expansion
- Develop GMP and detailed construction schedule at 90% design milestone
- Prepare construction delivery, staging, and site utilization plan
- Perform constructability and maintainability reviews at 45%, 60%, and 90% design
- Develop bidder interest and prequalify bidders for work packages
- Coordinate post-tension vs cast-in-place concrete construction options analysis
- Supervise construction of new sequencing batch reactor (SBR) trains
- Install and commission new 400 HP centrifugal blowers
- Coordinate plant operations during phased construction activities