Wild Oak Water Services Replacement and Pavement Preservation Project
4/28/2025
$4,784,193 for construction with 100 working days specified
Windsor, California
Town of Windsor
Buyer seeks professional services for construction management, inspection, and materials testing for a water infrastructure and pavement project. The project includes replacement of approximately 90 residential water service lines, 8,000 feet of water main, roadway resurfacing, and drainage improvements. The work will be conducted on Wild Oak Drive and adjacent streets in Windsor, California.
- 4/3/2025 - RFP Release Date
- 4/24/2025 - Last Day for Questions
- 4/28/2025 - Proposal Due Date
- 4/29/2025 - Construction Bid Opening
- 5/21/2025 - Town Council Awards Contracts
- 6/1/2025 - Construction Start
- Construction Manager with 10+ years of utility work experience
- Construction Inspector with 10+ years of experience, including underground utilities
- Manage construction of water main and service line replacements
- Conduct pre-construction review of contract documents
- Coordinate with Town, contractor, residents, and stakeholders
- Review and approve contractor submittals
- Inspect underground utility work and pavement preservation
- Monitor construction schedule and provide weekly status reports
- Conduct materials testing for asphalt concrete and cement concrete
- Process RFIs, change orders, and payment requests
- Perform labor compliance monitoring
- Document and resolve construction conflicts and claims