Quail Drive Water Loop Project
3/27/2025
-
Fraser, Colorado
Town of Fraser
The buyer seeks a contractor to complete the Quail Drive Water Loop Project. The work involves installing new water mains, replacing valves, and restoring disturbed areas. The project includes traffic control, dewatering, and materials testing. The contractor must coordinate with the buyer for water system connections and complete the project within 60 calendar days.
- 3/14/2025 - Pre-bid Meeting
- 3/19/2025 - Questions Due
- 3/27/2025 - Proposal Due Date
Refer to RFP
- Install approximately 175 LF of 6" C900 PVC water main
- Install approximately 192 LF of 8" C-900 PVC water main
- Replace existing 8" tee and valves with new 8" cross and valves
- Cut-in replacement of an existing 8" gate valve
- Install four 8" MJ gate valves and associated fittings
- Perform asphalt, concrete, and reseeding restoration of disturbed areas
- Provide traffic control and construction dewatering
- Conduct materials testing and quality control
- Coordinate with Town for water system connections and outages
- Complete project within 60 calendar days of Notice to Proceed